Suttle Piling have been awarded the design and installation of 109m of sheet piling work ranging between 4.2m to 5m in length at Buckmore Business Park near Petersfield by Mildren Construction. The site of a new Starbucks drive-thru adjacent to the BP Service Station.
Chris Booth, Piling Contracts Manager commented “Our in-house design team have specified GU13 interlocking steel sheet piles to form the proposed high strength sheeting system. This solution is ideally suited to support faces of large excavations. We will install the piles using the 22t Movax piling rig from our extensive self-operated fleet and anticipate completing the work, including mobilisation within two weeks.”
For more information on how Suttle Piling can support your ground engineering project objectives please visit https://www.suttlepiling.co.uk/ or email [email protected]