Another Job Well Done: Sheet Piling Success at Telham Embankment

In October, Suttle Piling successfully completed a technically challenging project to stabilise the railway embankment at Telham during a nine-day blockade for our client, BAM Nuttall. This work involved installing two lines of sheet piles, delivered on budget and ahead of schedule, while working under demanding site conditions.

Tackling Complex Rail Infrastructure Challenges

Railway embankments form a vital part of the UK’s transport infrastructure, but over time they can deteriorate due to weathering, ground movement, and increased usage. At Telham, the embankment required urgent stabilisation to maintain safety and reliability for rail services.

Suttle Piling was appointed to deliver this solution during a blockade period, when train services are temporarily suspended to allow construction works. With just nine days available, our team had to plan and execute every stage with precision.

Sheet Piling in Action

Our engineers installed two lines of sheet piles to provide long-term stability to the embankment. Sheet piling is often the most efficient method in rail environments, as it:

  • Provides robust earth retention and slope stabilisation.
  • Can be installed quickly, minimising disruption to rail services.
  • Reduces the footprint of the works compared to alternative solutions.

At Telham, this method ensured the embankment was secured safely and effectively within the tight timescale.

Working Safely Under Challenging Conditions

The project was not without its complexities. Our crews operated 24 hours a day in rotating shifts, maximising productivity during the blockade. Adding to the challenge, the works were carried out beneath live overhead power lines, requiring strict adherence to safety procedures and coordination with BAM Nuttall and rail authorities.

Despite these pressures, the project was delivered ahead of schedule, a testament to the skill, commitment, and careful planning of our team.

A Trusted Partner for Rail Projects

This project highlights Suttle Piling’s ability to deliver for clients in the rail and infrastructure sectors, where time, safety, and reliability are critical. By combining specialist equipment with experienced site teams, we help clients like BAM Nuttall meet their objectives while ensuring minimal disruption to the public.

Delivering Value for Clients

By completing the works on budget and ahead of schedule, we not only safeguarded the railway infrastructure but also demonstrated the efficiency and value we strive to provide in every project.